Denison Mines Corp. is pleased to announce the completion of commissioning of the lixiviant injection system for the Phoenix in-situ recovery (“ISR”) Feasibility Field Test (“FFT”) at the Company’s 95% owned Wheeler River project (“Wheeler River” or the “Project”).
Kevin Himbeault, Denison’s Vice President of Plant Operations & Regulatory Affairs, commented, “With the completion of construction and wet commissioning of the injection modules, we have now successfully commenced our initial injection of lixiviant into the test area, which represents the beginning of the leaching phase of the FFT.“
David Cates, Denison’s President and CEO, added, “We are proud of this notable milestone, particularly given the extensive coordination and efforts of Denison‘s Saskatoon-based technical team and our various construction partners that have delivered on the safe and timely construction and commissioning of this first-of-its-kind test facility.“
Limited construction activities continue on-site to support future phases of the FFT (discussed below). Construction efforts for the FFT are being completed in collaboration with Tron Construction & Mining, a well-established operator in northern Saskatchewan that is part of the Des Nedhe Group and owned 100% by English River First Nation. Civil earthworks for the FFT are substantially completed, and continue to be supported by Snake Lake Contracting, another northern Saskatchewan-based and Indigenous-owned business.
This press release constitutes a “designated news release” for the purposes of the Company’s prospectus supplement dated September 28, 2021 to its short form base shelf prospectus dated September 16, 2021.
The FFT is designed to use the existing commercial-scale ISR test pattern (“Test Pattern”), installed at Phoenix in 2021 (see news releases dated July 29, 2021, and October 28, 2021), to facilitate a combined assessment of the Phoenix deposit’s hydraulic flow properties with the leaching characteristics that have been assessed through the metallurgical core-leach testing program.
The FFT is fully permitted, having been authorized by both the Saskatchewan Minister of Environment (see news release dated July 12, 2022) and the Canadian Nuclear Safety Commission (see news release dated August 8, 2022).
Overall, the FFT is intended to provide further verification of the permeability, leachability, and containment parameters needed for the successful application of the ISR mining method at Phoenix and is expected to validate and inform various feasibility study design elements – including the expected production and remediation profiles.
The operation of the FFT is planned to occur in three phases: (1) the leaching phase, (2) the neutralization phase, and (3) the recovered solution management phase.
The leaching phase is designed to assess the effectiveness and efficiency of the leaching process in the mineralized zone, which is approximately 400m below the surface. The leaching phase includes the controlled injection of an acidic solution into a portion of the existing Test Pattern within the mineralized zone (the “Leaching Zone”) and the recovery of the solution back to the surface using existing test wells. The recovered solution from the leaching phase is expected to contain dissolved minerals, including uranium, copper, iron, molybdenum, and zinc.
The neutralization phase involves the recovery of the remainder of the leached mineralized solution from the Leaching Zone and is intended to verify the efficiency and effectiveness of the process for returning the Leaching Zone to environmentally acceptable conditions. During this phase, a mild alkaline (basic) solution will be injected into the Leaching Zone to neutralize the area and reverse the residual effects of the acidic solution injected during the leaching phase.
The recovered solution management phase involves separating the solution recovered from both the leaching phase and the neutralization phase into (i) mineralized precipitates and (ii) a neutralized treated solution.
Wheeler River is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca Basin region, in northern Saskatchewan – including combined Indicated Mineral Resources of 132.1 million pounds U3O8 (1,809,000 tonnes at an average grade of 3.3% U3O8), plus combined Inferred Mineral Resources of 3.0 million pounds U3O8 (82,000 tonnes at an average grade of 1.7% U3O8). The Project is host to the high-grade Phoenix and Gryphon uranium deposits, discovered by Denison in 2008 and 2014, respectively, and is a joint venture between Denison (operator) and JCU (Canada) Exploration Company Limited (“JCU”). Denison has an effective 95% ownership interest in Wheeler River (90% directly, and 5% indirectly through a 50% ownership in JCU).
A PFS was completed for Wheeler River in 2018, considering the potential economic merit of developing the Phoenix deposit as an ISR operation and the Gryphon deposit as a conventional underground mining operation. Taken together, the Project is estimated to have mine production of 109.4 million pounds U3O8 over a 14-year mine life, with a base case pre-tax NPV of $1.31 billion (8% discount rate), Internal Rate of Return (“IRR”) of 38.7%, and initial pre-production capital expenditures of $322.5 million. The Phoenix ISR operation is estimated to have a stand-alone base case pre-tax NPV of $930.4 million (8% discount rate), IRR of 43.3%, initial pre-production capital expenditures of $322.5 million, and industry-leading average operating costs of US$3.33/lb U3O8. The PFS is prepared on a project (100% ownership) and pre-tax basis, as each of the partners to the Wheeler River Joint Venture are subject to different tax and other obligations.
Further details regarding the PFS, including additional scientific and technical information, as well as after-tax results attributable to Denison’s ownership interest, are described in greater detail in the NI 43-101 Technical Report titled “Pre-feasibility Study for the Wheeler River Uranium Project, Saskatchewan, Canada” dated October 30, 2018, with an effective date of September 24, 2018. A copy of this report is available on Denison’s website and under its profile on SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.shtml.
Denison suspended certain activities at Wheeler River during 2020, including the EA process, which is on the critical path to achieving the project development schedule outlined in the PFS. While the EA process has resumed, the Company is not currently able to estimate the impact to the project development schedule outlined in the PFS, and users are cautioned against relying on the estimates provided therein regarding the start of pre-production activities in 2021 and first production in 2024.
Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of northern Saskatchewan, Canada. In addition to its effective 95% interest in the Wheeler River project, Denison’s interests in the Athabasca Basin include a 22.5% ownership interest in the McClean Lake joint venture, which includes several uranium deposits and the McClean Lake uranium mill that is contracted to process the ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest Main and Midwest A deposits, and a 67.01% interest in the Tthe Heldeth Túé (“THT,” formerly J Zone) and Huskie deposits on the Waterbury Lake property. The Midwest Main, Midwest A, THT and Huskie deposits are each located within 20 kilometres of the McClean Lake mill.
Through its 50% ownership of JCU, Denison holds additional interests in various uranium project joint ventures in Canada, including the Millennium project (JCU 30.099%), the Kiggavik project (JCU 33.8118%) and Christie Lake (JCU 34.4508%). Denison’s exploration portfolio includes further interests in properties covering approximately 300,000 hectares in the Athabasca Basin region.
Denison is also engaged in post-closure mine care and maintenance services through its Closed Mines group, which manages Denison’s reclaimed mine sites in the Elliot Lake region and provides related services to certain third-party projects.